Hang off Platforms

Summary:
AMICON is fully responsible for the entire supply of all necessary Hang off Platforms for Windpark Hollandse kust Noord. Hollandse kust Noord is a wind farm located in the Northsea in front of the coast of the province Noord-Hollandse. 70 Wind turbines will be installed in the park, with each turbine provided with an Hang off Platform. The park will have an installed power off 759 MW and a generates at least 3,3 TWh per year. AMICON has played a major role in the development of this product in this project. Our engineering has developed a fully customised product for this project.

Specifications:
*Number of platforms: 70
*Main structure material: S355J2+N
*Material various parts: Aluminium ladder, RVS316L earthing studs, Duplex 1.4462 clamps
*Manufactured according to EN 1090-2 EXC2

Coating:
Amicon has set up an in-house blasting and coating cabin at its production location in Sneek to provide all 70 platforms with a 3-layer C4X coating system. The sand blasting and coating of the platforms is carried out completely by Amicon and checked for quality according to our internal procedures. In addition to the coating system, all railings and various cable and ladder supports are hot-dip galvanized.

Assembly:
The complete Hang off Platform is assembled at our location in Sneek. The several parts are built into one whole onsite. After the structure has been completely assembled, the cable trays, earth cables, platforms and ladders will be installed and the platforms will be tested in the presence of the customer.

Transport:
In addition to manufacturing and assembly, AMICON provides all of the transport, by water, of the Hang off Platforms to Rotterdam. The Hang off Platforms will be loaded at the quay in Sneek and shipped to the storage quay by means of inland vessels (DAP = Delivery At Place).

Scope of delivery:

For more information about this project, please visit the website of The Windfarm.